Date | Deliverables |
---|---|
Sep 3 — Plan | Plan · Presentation |
Sep 29 — Milestone 1 | Requirement · Design · Test · Presentation · Progress Evaluation |
Oct 27 — Milestone 2 | Presentation · Progress Evaluation |
Nov 24 — Milestone 3 | Presentation · Progress Evaluation |
Date | Deliverables |
---|---|
Sep 3 — Plan | Plan · Presentation |
Sep 29 — Milestone 4 | Presentation · Progress Evaluation |
Oct 27 — Milestone 5 | Poster · Presentation · Progress Evaluation |
Nov 24 — Milestone 6 | User and/or Developer Manual · Demo Video · Presentation · Progress Evaluation |